Learning is just a part of our life. We do not hope that you spend all your time on learning the AACE-PSP certification materials. Life needs balance, and productivity gives us a sense of accomplishment and value. So our AACE-PSP real exam dumps have simplified your study and alleviated your pressure from study. It is our goal that you study for a short time but can study efficiently. At present, thousands of candidates have successfully passed the AACE-PSP Exam with less time input. In fact, there is no point in wasting much time on invalid input. As old saying goes, all work and no play makes jack a dull boy. Our AACE-PSP certification materials really deserve your choice. Contact us quickly. We are waiting for you.

To be eligible for the AACE-PSP certification, candidates must have a minimum of four years of professional experience in planning and scheduling. They must also have a bachelor's degree or higher in engineering, construction management, business administration, or a related field. Alternatively, candidates with eight years of professional experience in planning and scheduling can also apply for the certification without a bachelor's degree.

AACE International is a globally recognized authority in project management, cost engineering, and controls. The AACE-PSP Certification Exam is an industry-recognized certification that validates the skills and knowledge of professionals in project planning and scheduling. Planning & Scheduling Professional (PSP) Exam certification is designed to assess the proficiency of professionals in project planning and scheduling by testing their ability to apply the best practices and techniques in project management.

>> Valid AACE-PSP Test Book <<

AACE International Valid AACE-PSP Test Book | Useful AACE International Reliable AACE-PSP Exam Materials: Planning & Scheduling Professional (PSP) Exam

We boost the professional and dedicated online customer service team. They are working for the whole day, weak and year to reply the clients' question about our AACE-PSP study question and solve the clients' problem as quickly as possible. If the clients have any problem about the use of our AACE-PSP Exam Practice materials and the refund issue they can contact our online customer service at any time, our online customer service personnel will reply them quickly. So you needn’t worry about you will encounter the great difficulties when you use our AACE-PSP test pdf.

The AACE-PSP Certification Exam is an excellent way for professionals in the planning and scheduling field to demonstrate their expertise and advance their careers. With its worldwide recognition and rigorous testing standards, the AACE-PSP Certification Exam is a respected credential that can help professionals stand out in a competitive job market.

AACE International Planning & Scheduling Professional (PSP) Exam Sample Questions (Q79-Q84):

NEW QUESTION # 79
Which of the following phases does NOT describe the commonly accepted construction life cycle?

  • A. Turnover and start-up phase.
  • B. Planning and design phase.
  • C. Installation phase.
  • D. Claims and disputes phase.

Answer: B


NEW QUESTION # 80
Theoretically construct a summary activity for activities 6001 through 6003. Identify the governing predecessor and successor activities for the hammock:

  • A. Predecessor is activity 5001, successor is activity 8001
  • B. Predecessor is activity 4001, successor is activity 8001
  • C. Predecessor is activity 9001, successor is activity 9002
  • D. Predecessor is activity 5001, successor is activity 8002

Answer: A


NEW QUESTION # 81
All the following describe the critical path of a schedule EXCEPT:

  • A. Frequently defined as the shortest path through the schedule.
  • B. The series of activities having the least amount of total float.
  • C. Changed by redefining the network logic or changing activity durations or both.
  • D. Determined by network logic and is the chain of activities that controls the overall project completion time.

Answer: B


NEW QUESTION # 82
Which of the following project planning situations is the most frequent contributor to cost overruns?

  • A. Inappropriate definition of work breakdown structure
  • B. lack of detailed planning for operational start-up
  • C. Inadequate definition of scope at the estimate (budget) stage
  • D. Insufficient planning for change management

Answer: C


NEW QUESTION # 83
What is the workweek period for this project?

  • A. Sunday through Friday
  • B. Monday through Saturday
  • C. Monday through Friday
  • D. Sunday through Saturday

Answer: D


NEW QUESTION # 84
......